Six International Lenders Back US$588 Million Financial Close of 900 MW Onshore Wind Farm in Egypt

A consortium of six international lenders has provided approximately US$588 million in project financing for the development of the 900 MW Gulf of Suez III Wind Farm in Egypt, with the Japan Bank for International Cooperation (JBIC) committing up to US$285 million towards the facility.

JBIC signed the project finance loan agreement with Shokeir Wind Energy S.A.E., the Egyptian project company developing the wind farm. The financing consortium comprises JBIC, Société de Promotion et de Participation pour la Coopération Economique (PROPARCO), the Netherlands Development Finance Company (FMO), Société Générale, Crédit Agricole and KfW IPEX-Bank. The portions provided by private financial institutions benefit from insurance coverage by Nippon Export and Investment Insurance (NEXI). HSBC Bank Egypt is acting as the working capital facility bank and onshore security agent.

The financing also includes separate equity bridge loan arrangements, with KfW providing financing for ENGIE, Mizuho for Aeolus, and FMO and British International Investment (BII) for Orascom Construction.

The project reached financial close on 12 November 2026 and is being developed by Shokeir Wind Energy, jointly owned by ENGIE (35%), Orascom Construction (25%) and Aeolus (40%). ENGIE is the lead developer of the project, which is located near Ras Shokeir along Egypt's Gulf of Suez.

The development is supported by a 25-year power purchase agreement with the Egyptian Electricity Transmission Company (EETC), whose obligations are backed by Egypt's Ministry of Finance. The project also benefits from a 25-year usufruct agreement with the New and Renewable Energy Authority for the use of the project land.

Orascom Construction will undertake the balance of plant works, including the on-site high-voltage substation, while Goldwind will supply, install and commission the wind turbines. The wind farm will be connected to the national grid in three phases, with the first 300 MW expected to enter commissioning in January 2028 and full commercial operations targeted for the third quarter of 2028.

Once operational, the wind farm is expected to generate approximately 4 TWh of renewable electricity annually, making it ENGIE's largest onshore wind farm worldwide. It is the third wind energy project developed by ENGIE and its partners in Egypt, following the 262.5 MW Ras Ghareb wind farm and the 650 MW Red Sea Wind Energy project. Together, the three developments will represent approximately 1.8 GW of wind generation capacity in the country.

Ashurst Perkins Coie advised ENGIE, Orascom Construction and Aeolus on the financing, with Marei, Fayez, Dardiry & Partners acting as Egyptian counsel to the sponsors.